Last week the tin roof on the scaffold was removed as we have now finished the roof. Tomorrow (16-5-14) we will fit the bathroom window and door which we have been waiting for. The plastering has been done and the guys are working on the small bathroom in the loft. The small boiler was fitted upstairs and the soil pipe was also extended to join with the downstairs bathroom. The VELUX windows have been fitted and the project is nearing completion.

Please see some recent photos taken today (15-5-14)

The competed ones were taken with a mobile phone so the quality is not that great.

Click here to see earlier updates.